Building a pole barn in Michigan's UP in winter

Mike:

The Soo is an abreviation and a twist on the anglicized pronounciation of Sault Ste. Marie a pair of communities with the same name on both sides of the river, one in Michigan and one in Ontario. Sault is actually prounounced similar to the word sew. Sault means a rapid as in a river which is what Sault Ste. Marie is named for -- the rapids in the St. Mary River. The Soo Canals were built to go around the rapids.
 
Cowboy":w852vpp8 said:
It was $34,145 materials taxes and built. Or the price of a new pickup truck which is the way we looked at it.

Great looking barn. You made the right choice. Barn vs. new truck, barn wins out every time. It will last longer and the good thing is, it will go up in value.
 
Thanks Jim

Just as a side note a lot of times you can get a 10% discount on buildings if you order them in january. Even if they do not build them until latter in the year.

Billy
 
wow you have defined "work" at a whole new level., great job! Shed is mighty fine.

My wife and I visit the Ironwood area every summer, is that far from your neck of the woods /eah'
Take care, Jim
 
Nice building. Great job on the photos. Showed em to a few pals and we are all envious of it.

I always thought things were bigger in Texas, but you done my Michigan heritage proud!
 
Thanks Jim

I had to look up Ironwood. I have heard the name but did not know exactly where it was. Its all the way across the UP from me. I am 25-30 miles east of I-75 In Pickford MI. I am not much for building I can do some but am slow about it. But I love dirt work and can go from daylight to dark anytime.

Thanks Larry

It was fun but a big relief to get all that done. There is still a lot to do. But now that I have some where to work out of it will make things a lot easier. I can start a project and not have to worry about finishing it in one weekend.

Billy
 
Just up dating my pole barn with some of the work I got done in the front last fall. When I got done filling in the barn I had a 5% grade infront of it. I had to build up the parking/entry area 4' with dirt then topped it with 14" of stone.

182293_1484810175183_1681757389_900438_7228525_n.jpg


After filling with dirt

184332_1484816055330_1681757389_900442_139242_n.jpg


Stoning the parking area.

184332_1484816095331_1681757389_900443_5627836_n.jpg


38332_1271788009762_1681757389_517745_722454_n.jpg


38319_1271791289844_1681757389_517770_3743206_n.jpg


Finished the pad

38332_1271788089764_1681757389_517747_569386_n.jpg


184332_1484816215334_1681757389_900445_3428885_n.jpg


Billy
 
In November I got back up and built the front drive. I had a pile of logs to clean up that I saved when I cleared the woods to make the building pad. Most of them were too small to cut lumber out of so they were cutup for firewood. The rest went to the saw pile.

183924_1484843136007_1681757389_900491_4815156_n.jpg


Looking down the new drive from the barn.

184320_1484825415564_1681757389_900453_2378519_n.jpg


75778_1369662176555_1681757389_703158_2772647_n.jpg


75778_1369662216556_1681757389_703159_6269189_n.jpg


From the shed

184320_1484825455565_1681757389_900454_6401824_n.jpg


75778_1369662336559_1681757389_703162_2370045_n.jpg


I have a lot of work to do on the side road and back. But it sure is nice when it comes together!

Billy
 
Whatever construction materials you choose, will give you a good shop. If you can afford it, go with the concrete floor, throughout. Cleaner, dryer, and safer, if you need to jack a parked machine. Ed
 
Thanks Steve

That is my spare time I have been laid off for over a year now. But things are looking good for a job this year.

Thanks Bill E Bob

What can I say I love playing in the dirt. Guess I never grew up.

Thanks Ed

We planed on concreting the first 30' but since then decided it would be best to leave that one open for parking. And build a 30x40 concrete floor 2x6 stud wall for our shop and work area. Closing off a area for heated work room would have made the big barn hard to park in. With all the toys we have we need more room anyway. My brother wants to put a lean-to on the big one but with all the snow up there I don't want to make it any wider than it is.

Billy
 
i spent some time in the up in 1994 at my buddies wedding . flew in on a puddle jumper, drove from saginaw,michigan, north, across "THE BRIDGE", and then all the way west , almost to hurley. wedding was outside at indian point. you youpers are a HARDY bunch !! val (very impressed) a. , coppersmythe.......................
 
Yep Copper.... it's a whole different world up there. But, then again they were still making Cubs last time I was in the UP. I will never forget the sound of the ice 'moving' in the winter at St Ignace..... eerie!
 
Thanks Larry

Ya know they are never big enough! I can't wait to get UP there again I'm going stir crazy sitting around the house just feeding my horse.

Thanks Coppersmythe

I live down state but and ready to move UP!!!

Billy
 
I was at the farm for the last two weeks getting all the dirt work done around the outside of the barn. The back door was almost unusable. As it was built into the side of the hill and the hill side was too close to the door. It also needed the temporary ditches moved back and permint one put in. I had to clear all the woods off first and make a place to put all the dirt I had to remove. I used the dirt I removed to make a 20' tall pyramid that is going to be the base of my observation tower that I am also going to put my wind generators on.

Here's the back of the barn as I left it last year

251754_1620956338752_1681757389_1087790_7305344_n.jpg


The ground was a hardpan with rocks and boulders and my little dozer would barley cut it but the excavator didn't have much problem.

264296_1656544508434_1681757389_1131172_948588_n.jpg


I also had to clear the woods for a area to dump the dirt. And make a road to get the truck back there.

264196_1656539188301_1681757389_1131163_6803828_n.jpg


264196_1656539228302_1681757389_1131164_2421996_n.jpg


Since I am going to use the dirt for the base of my tower and I want it compacted not loose. I put it in in lifts. Which means I dumped it spread it out 1' thick and ran the dump truck over it to pack it down.

264296_1656544548435_1681757389_1131173_5857464_n.jpg


Got the south and west sides done. All the ground slopes away from the barn leaving it two feet higher than the ground around it so all the water runs away from the barn and stays out of the subgrade keeping dry in and under the barn. I dug it back 60' from the back door to leave me plenty of room to pull trailers through and park equ.

264296_1656544588436_1681757389_1131174_1852477_n.jpg


The back of the barn done other than hualing in and spreading gravel for the parking area.

264296_1656544668438_1681757389_1131176_6517414_n.jpg


My dirt hill after I got it shaped up.

263027_1656521227852_1681757389_1131151_1641358_n.jpg


View from the top of the dirt pile. I always wanted a fire tower. I got some 20' pallet racks from Steve B a few years ago and I am going to put one up on top of the hill getting it above the trees giving me a really great view!

262677_1658874646686_1681757389_1134623_7652017_n.jpg


It was a lot of work and I burned over two hundred gallons of diesel fuel doing it. But it sure feels good to have it done!. Moving the dirt wasn't the hard part. The hard part was clearing all the trees and stumps off of it.

This is the fourth load of firewood I got off it that I gave to my Uncle. I also have eight cords more I have piled up for myself.

260292_1658879566809_1681757389_1134631_308316_n.jpg


A good sized pile of cedar spruce and pine for the sawmill.

260292_1658879526808_1681757389_1134630_8194289_n.jpg


And a decent little pile of brush for a campfire to relax around!

262677_1658874686687_1681757389_1134624_4108766_n.jpg